Dec. 22-23 - Painters start. Lots of taping and first coat of paint on walls, doors and trim. Shelves were built in closets.


Dec. 29-30 - Painters back to put second coat on walls, doors and trim.

Jan. 2 -Entrance doors painted. Second coat of paint on closet shelves and stairwell to Lockman house.

Jan. 5 - Vinyl and carpet ordered - Confirmed delivery of cabinets and appliances for Jan 15 - Installation set for Jan. 19.
Today, Jan. 8 - Entrance from Lockman house to addition done, first coat of mud applied

Sidewalk framed ready for concrete (weather permitting)