Jan. 12- Deck begins. Concrete blankets (thanks to Wayne and CMI) placed on framed sidewalk to keep ground warm for concrete delivery tomorrow. They worked great!!
Jan. 13 - Concrete truck arrives and sidewalk is completed. Alot of hand work was done throughout the day.




Lockman kitchen and entrance to Memaw's addition sanded. Third coat of drywall mud applied to both locations.



Vinyl arrives for kitchen and bathroom. Installer requests the roll of vinyl sit overnight in warm environment for installation tomorrow.
Quintin returns in late afternoon to cover sidewalk with concrete blankets. They will remain for a few days.